JAN 2018
PROJECT START DATE
PROJECT PERIOD
1 MONTHS
Commercial
Scottish Water
Maintenance
The project enabled works to comply with current Scottish Water ‘standards and specifications’ and ensured that the serviceability of the plant was secured by replacing poorly performing assets.
Scottish Water engaged their wastewater infrastructure alliance partner, ABV, to manage the overall scheme; however, the detailed design and delivery of the scheme was carried out by ABV’s own tier 1 alliance partner, Ferrier Pumps.


The entire station at Braehead was gutted andrefurbished with new pumps, screens, valves,actuators, MCCs, telemetry, security doors, gates, railings and walkways as well as security fences and covers.
The surrounding car park was also resurfaced.
The pumping station was kept fully operational throughout the construction period.