Project Cost
£ 1
NOV 2022
PROJECT START DATE
CONSTRUCTION PERIOD
1 MONTHS
Industrial
McLaughlin & Harvey
Wastewater Treatment
The scheme has been designed by Scottish Borders Council to reduce flood risk across Hawick. The scheme will protect against the effects of the 1 in 75 year flood event from the River Teviot.

During periods of heavy rain, the river level rises, and the WwTW is hydraulically unable to discharge via the existing gravity outlet, causing
flooding of the works.
Within the Hawick WwTW a new storm tank was constructed housing 4 submersible pumps. A steel gantry spans over the storage tank with an electric hoist to lift pumps for operational and maintenance purposes. An actuated valve was installed to divert flows when storm conditions arise. Instrumentation was installed within the tank monitoring levels for a fully automated system and a new kiosk housing an IMCC.